Our timeline
October 2021
H2NorthEast launched by Kellas Midstream
August 2022
H2NorthEast progresses into Track 1 Cluster Sequencing Process
March 2023
Funding secured through Net Zero Hydrogen Fund
Statera announced as first customer for H2NorthEast
December 2023
JV formed with SSE Thermal
November 2024
Successful FEED review by DESNZ
January 2025
FEED completion with partners Worley and Johnson Matthey
August 2028
Final Investment Decision
2033
Commencement of operation